Key points
- EIA is mandatory for large residential projects
- No approved EIA means no building permit
- Check the status before booking
Which projects need an EIA
For condominiums the threshold is 80 units or more, or more than 4,000 m² of usable area. Almost any apartment project by the sea in Phuket falls under this rule. Housing and villa estates have their own thresholds based on the number of plots and land area, so small villa projects usually do not need one.

Photo: AYANA Heights Seaview Residence, Layan, Phuket
Who approves it and how long it takes
The report goes to ONEP, the Office of Natural Resources and Environmental Policy and Planning. Staff review it first, then an expert committee considers it. Consultants budget six months to a year for the whole process, and longer if there are comments.
What happens without an EIA
- The developer cannot obtain a building permit, so construction cannot legally start.
- If the EIA is rejected, the project has to change: fewer floors, fewer units or a new layout.
- Sales sometimes start before approval. In that case the buyer's money depends on a decision that has not been made yet.

Photo: Sudara Phase 1, Bang Tao, Phuket
Why permits matter even after completion
A well-known example is Ashton Asoke in Bangkok, a joint venture of Ananda Development and Mitsui Fudosan. In 2023 the Supreme Administrative Court revoked the building permit of the finished 668-unit tower over an access issue. The authorities later offered a route to a new permit, but owners lived with uncertainty for a long time. It is not an EIA case as such, but it shows that project documents should be checked before buying, not after.
How to check the EIA status
- Ask the developer for the EIA approval number, date and a copy of the decision.
- Check the status in ONEP's system (Smart EIA Plus) by project name.
- Compare the approved parameters with the project: floors, number of units and area.
- If the EIA is still under review, the contract should give a refund if it is rejected, and the payment schedule should push the main amount to later stages.
We check the EIA and permits for every project in our catalogue before offering it to a client. More on other risks in Buying off-plan in Thailand: risks.
Why an EIA exists
A large residential complex changes everything around it: traffic, water, sewage, the beach and nature. The EIA assesses this impact before construction and sets conditions: how many floors and units may be built, how water is drained and which green areas must stay. For a buyer it is a sign that the project has passed review and will not be stopped halfway.
Examples
- A 50-unit condominium of 3,000 m²: usually no EIA needed.
- A 189-unit condominium in two buildings: an EIA is needed.
- An estate of 12 villas: usually no EIA, but a building permit is mandatory.
If there is no EIA yet: how to reduce the risk
- Pay only the minimum deposit before approval.
- Write a full refund into the contract if the EIA is not approved by a set date.
- Choose a developer that has had EIAs approved on similar projects.
- Track the status: we update project information in the catalogue.

Photo: Bellaguna Lotus, Bang Tao, Phuket
EIA and other permits
The EIA is not the only document. You also need the land title, the municipal building permit and, for a completed building, the occupancy certificate. More in How to check a developer.
Frequently asked questions
Does a small condominium need an EIA?
If it has fewer than 80 units and no more than 4,000 m² of usable area, an EIA is usually not required.
Can construction start before the EIA is approved?
No. Without an approved EIA the developer does not receive a building permit.
Can I buy while the EIA is under review?
You can, but the risk is higher. Make sure the contract allows a refund if it is rejected, and choose a schedule with the main payment near completion.
Where can I check the EIA status?
With the developer and in ONEP's system. We run this check for free.
How long does EIA approval take?
Usually six months to a year, longer if the committee has comments.